Grey Structure to Move In: What a Turnkey Handover Actually Includes

Grey Structure to Move In: What a Turnkey Handover Actually Includes

The grey structure is the easy half. What follows involves a dozen trades who all need to work in the right order, and that sequence is where most home projects lose months.

A grey structure looks like most of a house. Walls, slab, roof, the shape of every room. It feels close to finished. In practice it is roughly the halfway point, and the half that remains contains almost all the decisions, almost all the trades, and almost all the ways a project goes wrong.

This is what actually happens between a grey structure and a set of keys.

The sequence, and why order matters

The finishing stage is not a list of independent jobs. It is a sequence, and doing things out of order means undoing them.

  1. Survey and measurement. Every room measured as built, not as drawn. Grey structures rarely match the drawing exactly, and every later trade depends on the real numbers.
  2. Services first fix. Electrical conduit, plumbing runs, gas lines. All of this is buried, so it has to be right before anything covers it. Switch and socket positions should be decided against the furniture layout here, not later.
  3. Plaster and levelling. Walls and floors made true. Cabinetry built to an untrue wall will always show a gap.
  4. Flooring. Usually before joinery, so cabinets and wardrobes sit on the finished level.
  5. Ceilings. False ceilings, cove detail and recessed lighting. This has to coordinate with the electrical layout already run.
  6. Joinery and fixed interiors. Kitchen, wardrobes, doors, media walls, vanities. The largest single block of work.
  7. Worktops. Templated after cabinetry is installed, because they must match what was actually built.
  8. Paint and finishes. After the dust generating work is done.
  9. Services second fix. Switches, sockets, light fittings, taps and sanitary ware.
  10. Furniture and styling. Loose furniture, soft furnishing, final placement.
  11. Snagging and handover. The walk through where every defect is listed and fixed before you take the keys.

Where projects actually lose time

Almost never in the work itself. Delay collects in the gaps between trades.

The carpenter cannot start because the floor is not down. The floor is not down because the plaster is not cured. The electrician has finished but the ceiling contractor has not been booked, so the lighting cannot go in. Each of these is a small wait. Stacked across a dozen trades, they turn three months into eight.

The other reliable source of delay is decisions. Every trade needs an answer before it can start, and if the answer is still being discussed, the site simply stops.

Why splitting the work is expensive

Hiring each trade separately looks cheaper because each individual quote is lower. It is usually more expensive by the end, for three reasons.

  • Nobody owns the sequence. Each contractor optimises their own schedule, not the project.
  • Defects become arguments. When the wardrobe does not sit flush, the carpenter blames the plasterer and the plasterer blames the carpenter. You end up mediating.
  • Rework is unpriced. Chasing a wall to move a socket after the paint is done is a cost nobody quoted for, and it lands on you.

What to ask before you appoint anyone

  • Who holds the schedule, and who do I call when something slips?
  • Which items are in this scope, and which are excluded?
  • Who is responsible if two trades disagree about a defect?
  • Is the joinery made in your own facility or bought in?
  • What does the snagging process look like, and what happens after handover?

The last one is worth pressing on. Doors and drawers settle in the first weeks of use. A serious contractor expects to come back and adjust them.

How Grains handles it

Taking over at grey structure is our signature service. We survey the property, plan the sequence, and run every stage that follows through to handover, with the kitchen, wardrobes, doors and furniture manufactured at our own facility on Raiwind Road rather than bought in.

That means one schedule, one point of contact, and no gap between trades for a project to fall into. It also means that if something needs adjusting after you move in, the team that built it comes back.

If your structure is ready, or nearly, send us the address and the stage it is at on WhatsApp and we will arrange a site visit.

Good To Know

Questions, answered.

Turnkey means one company takes responsibility for every stage from the current condition of the property through to a finished, move in ready home. You deal with one schedule and one point of contact rather than coordinating separate contractors for electrical, plaster, flooring, joinery, paint and furniture.

Broadly: survey and measurement, services first fix, plaster and levelling, flooring, ceilings, joinery, worktops, paint, services second fix, furniture, then snagging and handover. Working out of this order usually means undoing completed work, which is where most cost overruns come from.

Each individual quote is usually lower, but the total often ends up higher. Nobody owns the sequence, gaps open between trades, defects turn into disputes between contractors, and rework caused by poor coordination is not in anyone original price.

Yes. We survey the property as it stands, confirm what has been completed and to what standard, and plan the remaining sequence from there. Send us the address and the current stage on WhatsApp and we will arrange a site visit.